| Workplan
Study Milestones/Status
- Study Kickoff Symposium – April 1999
- Base Mapping & Data Collection – Completed in spring 2000
- Corridor Identification (40+ alternatives) – Defined in April 2000
- Initial Corridor Screening – Completed in August 2000
- Second-level Corridor Impact Analysis – Completed in June 2001
- Technical Review and Public Outreach to Define Preferred Corridor(s) – On-going
- Draft Environmental Impact Statement (DEIS) – Completed in February 2002
- Public Hearing – Held in March 2002
- Comment Period – Closed April 30, 2002
- Preferred Corridor Identified – December 2002
- Obtain new detailed mapping of preferred corridors, 2003
- Develop preliminary highway designs, 2004
- Supplemental Environmental Impact Statement (SDEIS) – July 2006
- SDEIS Public Hearings – August 14-15-16, 2006
- SDEIS Public Comment Period – Closed August 31, 2006
- Developed additional Alignment Options for Segments 4 and 7
– Completed in August 2007
- USACE Highway Methodology Phase I Avoidance document
(Segments 4 and 7) – Completed October 2007
- USACE Highway Methodology Phase II Permit Application
(Segments 4 and 7) – Completed June 2008
- Presque Isle Bypass (Segment 7) Economic Impact Study – Completed November 29, 2007
- USACE Highway Methodology Phase II Permit Application (Segments 4 and 7) – Caribou Connector 1-161 Identified Preferred Alternative/Least Environmentally Damaging Practical Alternative (LEDPA) in September 2008 (Presque Isle Bypass under review at USACE)
- Tier 1 FEIS for ACTS and Tier 2 FEIS for Route 1-161 Connector in Caribou –
Completed December 2009
- ROD for Tier 1 FEIS for ACTS and Tier 2 FEIS for Route 1-161 Connector in Caribou –
Expected March 2010
- Tier 2 FEIS for Presque Isle Bypass – Expected completion September 2010
- ROD for Tier 2 FEIS for the Presque Isle Bypass – Expected December 2010
|
|